Sub Sector

Waste Water Treatment

Capital Value

£120m

start date

Jan 2022

Provision

Full SPV Management

Dalmuir Waste Water Treatment Works (WwTW) has been operated and maintained under a 25 year concession with Scottish Water, with revenues derived from volumes of waste water treated.

The plant has been designed for a full flow to effluent treatment of approx. 375,000m3/day or 137million m3/year. The site covers approximately 11.5 acres, located on the banks of the River Clyde, and provides a service to over 650,000 people throughout North West Glasgow, East Dunbartonshire and North Lanarkshire.

The original plant built in 1904 was a primary treatment facility before investment in 2001-2003 allowed secondary treatment and odour control to be incorporated. Further investment allowed a Capital Variation project in 2013-2015 which included the construction of 2no. Nitrate Trickling Filters (NTF’s) to assist in the secondary treatment process.